Solar inverter whitelist

How to get listed

Inverters over 800 VA may be operated in parallel with the grid in accordance with TOR Erzeuger (see chapter 8, among others) if the following documents are available:

  • Test reports from a test centre accredited for this subject area in accordance with ÖVE/ÖNORM EN ISO/IEC 17025 for inverter-based power generation systems with grid connection point at low voltage level in accordance with test standard OVE guideline R 25, in which documentation of the Austria setting or a manufacturer's parameterisation manual with the country settings "Austria" has also been confirmed.

or

  • Test reports of a testing body accredited according to ÖVE/ÖNORM EN ISO/IEC 17025 for this subject area for converter-based power generation systems with grid connection point on low voltage level according to VDE-AR-N 4105 or DIN VDE V0124-100 plus protocol of the delta test according to test standard ÖVE guideline R 25 Annex B.

In the test report itself there must be a complete documentation (screenshots) of the DEFAULT settings for country "Austria". Note: settings documented at the individual tests show only settings used for the specific test, not the default settings.

Please send the full test report to wechselrichter@oesterreichsenergie.at

For new devices, we reserve the right to verify the correct function of the country settings and their documentation using a test device.

Inverters over 800 VA may be operated in parallel with the grid in accordance with TOR Erzeuger (see chapter 8, among others) if the following documents are available:

  • Test reports from a test centre accredited for this subject area in accordance with ÖVE/ÖNORM EN ISO/IEC 17025 for inverter-based power generation systems with grid connection point at LV level in accordance with test standard OVE guideline R 25, in which documentation of the Austria setting or a manufacturer's parameterisation manual with the country settings "Austria" has also been confirmed.

or

  • Test reports of a testing body accredited according to ÖVE/ÖNORM EN ISO/IEC 17025 for this subject area for converter-based power generation systems with grid connection point on LV level according to VDE-AR-N 4105 or DIN VDE V0124-100 plus protocol of the delta test according to test standard ÖVE guideline R 25 Annex B.

In the test report itself there must be a complete documentation (screenshots) of the DEFAULT settings for country "Austria". Note: settings documented at the individual tests show only settings used for the specific test, not the default settings.

Please send the full test report to wechselrichter@oesterreichsenergie.at

For new devices, we reserve the right to verify the correct function of the country settings and their documentation using a test device.

Inverters over 800 VA may be operated in parallel with the grid in accordance with TOR Erzeuger (see chapter 8, among others) if the following documents are available:

  • Test reports from a test centre accredited for this subject area in accordance with ÖVE/ÖNORM EN ISO/IEC 17025 for inverter-based power generation systems with grid connection point at LV level in accordance with test standard OVE guideline R 25, in which documentation of the Austria setting or a manufacturer's parameterisation manual with the country settings "Austria" has also been confirmed.

or

  • Test reports of a testing body accredited according to ÖVE/ÖNORM EN ISO/IEC 17025 for this subject area for converter-based power generation systems with grid connection point on LV level according to VDE-AR-N 4105 or DIN VDE V0124-100 plus protocol of the delta test according to test standard ÖVE guideline R 25 Annex B.

In the test report itself there must be a complete documentation (screenshots) of the DEFAULT settings for country "Austria". Note: settings documented at the individual tests show only settings used for the specific test, not the default settings.

Please send the full test report to wechselrichter@oesterreichsenergie.at

For new devices, we reserve the right to verify the correct function of the country settings and their documentation using a test

Inverters over 800 VA may be operated in parallel with the grid in accordance with TOR Erzeuger (see chapter 8, among others) if the following documents are available:

  • Test reports from a test centre accredited for this subject area in accordance with ÖVE/ÖNORM EN ISO/IEC 17025 for inverter-based power generation systems with grid connection point at LV level in accordance with test standard OVE guideline R 25, in which documentation of the Austria setting or a manufacturer's parameterisation manual with the country settings "Austria" has also been confirmed.

or

  • Test reports of a testing body accredited according to ÖVE/ÖNORM EN ISO/IEC 17025 for this subject area for converter-based power generation systems with grid connection point on LV level according to VDE-AR-N 4105 or DIN VDE V0124-100 plus protocol of the delta test according to test standard ÖVE guideline R 25 Annex B.

In the test report itself there must be a complete documentation (screenshots) of the DEFAULT settings for country "Austria". Note: settings documented at the individual tests show only settings used for the specific test, not the default settings.

Please send the full test report to wechselrichter@oesterreichsenergie.at

For new devices, we reserve the right to verify the correct function of the country settings and their documentation using a test device.

Inverters over 800 VA may be operated in parallel with the grid in accordance with TOR Erzeuger (see chapter 8, among others) if the following documents are available:

  • Test reports from a test centre accredited for this subject area in accordance with ÖVE/ÖNORM EN ISO/IEC 17025 for inverter-based power generation systems with grid connection point at LV level in accordance with test standard OVE guideline R 25, in which documentation of the Austria setting or a manufacturer's parameterisation manual with the country settings "Austria" has also been confirmed.

or

  • Test reports of a testing body accredited according to ÖVE/ÖNORM EN ISO/IEC 17025 for this subject area for converter-based power generation systems with grid connection point on LV level according to VDE-AR-N 4105 or DIN VDE V0124-100 plus protocol of the delta test according to test standard ÖVE guideline R 25 Annex B.

In the test report itself there must be a complete documentation (screenshots) of the DEFAULT settings for country "Austria". Note: settings documented at the individual tests show only settings used for the specific test, not the default settings.

Please send the full test report to wechselrichter@oesterreichsenergie.at

For new devices, we reserve the right to verify the correct function of the country settings and their documentation using a test device.

device.